Tru Blu installation & ownership guide

UV system installation

Install the included Insnrg Ui in its intended return-line position and preserve access to the lamp.

Use this guide with the installation detail and equipment manuals supplied with your pool. Your site approval sets the required inspections.

Chamber position

  1. Install the Ui vertically in the return line, using the supplied layout and manufacturer flow direction. The Ui manual specifies placement before any additional sanitising device.
  2. Allow at least 300 mm above the chamber for lamp removal. Keep service unions accessible and support connected pipework.

Ballast and power

  1. Mount the electronic ballast securely under cover, away from rain, direct sun and sprinkler splash. Use the supplied manual’s mounting requirements.
  2. Arrange electrical supply and protection through a licensed electrician. Never view an exposed operating UV lamp or bypass interlocks.

Startup

  1. Check the chamber and unions for leaks once circulation is established. Confirm the ballast indicator and lamp operation as the manual describes.
  2. Synchronise operation so the UV runs with circulation rather than treating it as a separate always-on appliance.

Ongoing care

  1. Check indicators and keep the ballast dry. Arrange lamp and quartz-sleeve service according to the manufacturer schedule.
  2. UV treats water flowing through the chamber and leaves no protective residual in the pool. Maintain the specified chlorine residual and water testing.

Service envelope and timing

  1. Mount the chamber vertically with at least 300 mm clear above its top for lamp service. Its manual shows a 545 mm chamber height, giving an 845 mm chamber-plus-clearance envelope. Allow additional space for the mounting and pipework.
  2. Use opaque inlet pipework and position the electronic ballast under shelter. The licensed electrical installer sets the protected supply and coordinated pump/UV operation.

Illustrated installation manual

Work through the drawings and job checks below, or download the same sequence as a PDF. Open a drawing to zoom into its labels.

01Lay out the equipment station

Lay out the equipment station: installation diagram; read the accompanying steps for the construction detail
Functional illustration. Use the dimensions and assembly details identified in the accompanying instructions.
  1. Place the pump, filter and UV where each service part can be reached. Mark the actual equipment footprints on the pad before drilling or gluing.
  2. Keep the pump motor ventilated and the equipment area drained. Avoid roof runoff, persistent flooding and enclosed chemical storage.
  3. Keep isolation valves and unions on accessible faces. Leave room to lift lids and remove components.
  4. Plan cables and electrical isolation with the electrician. Equipment must not create a climbable route past the pool barrier.

The equipment-pad size follows the actual service envelopes. A generic rectangle is not sufficient if a lid or lamp cannot be removed.

02Mount and prime the pump

Mount and prime the pump: installation diagram; read the accompanying steps for the construction detail
Functional illustration. Use the dimensions and assembly details identified in the accompanying instructions.
  1. Inspect the supplied pump, basket, lid seal and unions. Place it securely on the level pad without pipe strain.
  2. Connect suction to the inlet and discharge to the filter. Align the pipework; do not force the pump unions into position.
  3. Before first operation, fill the priming chamber as directed in the pump manual, fit the lid seal correctly and open the circulation path.
  4. Have the electrical supply and required bonding completed by the licensed electrician. Start only when primed; stop if it fails to establish circulation.
Job check / record
  • Pump model / serial
  • Priming completed
  • Supply certificate reference

The prototype pump was a Davey Whisper W500. Match the installed pump model to its supplied operating instructions.

03Give the cartridge room to come out

Give the cartridge room to come out: installation diagram; read the accompanying steps for the construction detail
Functional illustration. Use the dimensions and assembly details identified in the accompanying instructions.
  1. For Davey CrystalClear 39050, reserve 835 mm total height from the base for cartridge removal. The body height is 540 mm. Leave useful access around the lid and gauge.
  2. Orient the chosen INLET toward pump discharge and connect OUTLET to the filtered return circuit. Close the unused inlet with the supplied cap.
  3. Use the supplied O-ring unions, clean seals and hand tightening. Support both pipe runs independently.
  4. Bleed trapped air during startup according to the filter manual and record the clean-filter pressure.
Job check / record
  • Filter model / serial
  • Clean-filter pressure (kPa)
  • Cartridge-removal space checked

Dimensions shown are for 39050 only. A replacement model can have a different service envelope.

04Install the vertical UV chamber

Install the vertical UV chamber: installation diagram; read the accompanying steps for the construction detail
Functional illustration. Use the dimensions and assembly details identified in the accompanying instructions.
  1. Put Insnrg Ui in the filtered return line before any other sanitising device. Keep the chamber vertical and the inlet pipe opaque.
  2. Leave at least 300 mm clear above its top. A 545 mm chamber plus that clearance occupies 845 mm before mounting offsets or pipework.
  3. Mount the ballast under shelter; keep connections accessible. Arrange protected power and coordinated pump/UV operation with the electrician.
  4. Complete the wet leak check before enabling UV. Keep the housing assembled and never look at an exposed operating UV lamp.
Job check / record
  • UV model / serial
  • Overhead clearance measured
  • Pump / UV timer coordination

Mount the ballast securely under shelter and beyond splash exposure, with its leads and isolation accessible.

05Reserve airflow for the Hi35

Reserve airflow for the Hi35: installation diagram; read the accompanying steps for the construction detail
Functional illustration. Use the dimensions and assembly details identified in the accompanying instructions.
  1. For the front-discharge Hi35 manual 250926, keep at least 1,000 mm clear in front and 500 mm at each side and behind, with open ventilation above.
  2. Orient discharge away from nearby obstructions and avoid cold-air recirculation. Keep routine service access as well as airflow space.
  3. Set the unit level and provide condensate drainage. Do not carry or lift it by its water unions.
  4. Arrange licensed electrical connection. Refrigerant work belongs to qualified refrigeration personnel.
Job check / record
  • Heat pump model / discharge type
  • Front / side / rear clearances
  • Condensate route

These clearances apply to the referenced front-discharge range, not a top-discharge model.

06Commission the heating option

Commission the heating option: installation diagram; read the accompanying steps for the construction detail
Functional illustration. Use the dimensions and assembly details identified in the accompanying instructions.
  1. Start circulation and check water flow before enabling the heater. Inspect its unions and bypass for leaks.
  2. Set the supplied bypass so the heater receives its model-required flow. Record inlet and outlet readings once operation is stable.
  3. Check that loss of circulation stops heating, following the manufacturer commissioning procedure. Restore the normal operating settings.
  4. Record model, serial, setpoint and bypass position. Keep controls accessible and show the owner how to isolate the heater safely.
Job check / record
  • Inlet / outlet water temperatures
  • Bypass setting / setpoint
  • Flow-stop check
  • Commissioning date / installer

Use the heat-pump manual for its operating range and flow adjustment; pool diameter alone does not determine the bypass setting.

Manufacturer instructions & references

Keep the instructions for your exact supplied model with this guide.

Davey CrystalClear manual ↗Insnrg equipment manuals ↗

Completion checklist